A project team is full of ideas but repeatedly fails to turn them into workable plans and schedules. Using Belbin's framework, which role is the team most likely to be lacking?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) Implementer
Explanation
The Implementer is disciplined and practical, turning ideas and concepts into workable procedures and plans. A team rich in ideas but poor at execution already has creative input (Plant, Resource investigator) and lacks the practical organiser. A Teamworker supports harmony within the team but does not specifically convert ideas into action.
Practise all 11 Chapter 10 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 11 questions in Chapter 10Individual, group and team behaviour MCQs with answersNext chapter · Chapter 11Motivating individuals and groupsACCA BT question bank · 14 chapters
More Individual, group and team behaviour MCQs
- Q7Charles Handy described four types of organisational culture. Which culture is characterised by a central source of power, such as an…
- Q8A government department relies on detailed job descriptions, formal procedures and clearly defined hierarchy, and values stability and…
- Q9Edgar Schein identified three levels of organisational culture. Which of the following is an example of an 'artefact' (the most visible…
- Q10In Hofstede's research on national cultures, a society in which people generally accept that power is distributed unequally and expect…
- Q11Which of the following is generally regarded as a characteristic of an effective team?