ACCA FM · Chapter 8 · Question 5 of 10
A company has $300k of capital available. The following independent projects are indivisible ($000): A outlay 120, NPV 30; B outlay 180, NPV 40; C outlay 150, NPV 39; D outlay 100, NPV 20. Which combination of projects should be undertaken?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) Projects A and B, total NPV $70k
Explanation
With indivisible projects, every feasible combination must be tested. Feasible pairs within $300k: A+B (300, NPV 70), A+C (270, NPV 69), A+D (220, NPV 50), B+D (280, NPV 60), C+D (250, NPV 59); no three projects fit. A+B gives the highest NPV of $70k. Ranking by profitability index (C 0.26, A 0.25) would select A and C, leaving $30k unused and giving only $69k.
Practise all 10 Chapter 8 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 10 questions in Chapter 8Asset replacement, capital rationing and lease or buy MCQs with answersNext chapter · Chapter 9Risk and uncertainty in investment appraisalACCA FM question bank · 14 chapters
More Asset replacement, capital rationing and lease or buy MCQs
- Q7In a lease versus buy decision, which discount rate should normally be used to discount the financing cash flows?
- Q8A company can buy a machine for $100,000 at the start of year 1 (time 0) (4-year life, no residual value) or lease it for $28,000 a year…
- Q9A project requires an initial investment of $180,000 and the present value of its future net cash inflows is $225,000. Defining the…
- Q10Capital is expected to be limited in more than one future period. Which technique is most appropriate for selecting projects to maximise…
- Q1A machine costs $60,000. Running costs are $10,000 in year 1, $14,000 in year 2 and $18,000 in year 3. Its resale value is $30,000 after 2…
