ACCA LW · Chapter 4 · Question 3 of 10
A laundry company bought a boiler that was delivered five months late. The seller knew the laundry needed it urgently but did not know of an especially lucrative government dyeing contract. Following Victoria Laundry v Newman Industries, which losses could the laundry recover?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) The normal profits lost through the delay, but not the exceptional profits from the government contracts
Explanation
The seller knew the boiler was needed for immediate use, so ordinary lost profits were within reasonable contemplation and recoverable. The highly lucrative government contracts were not known to the seller, so the extra profits were too remote under the second limb of Hadley v Baxendale. Lost profits are recoverable in principle if not too remote.
Practise all 10 Chapter 4 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 10 questions in Chapter 4Breach of contract and remedies MCQs with answersNext chapter · Chapter 5The law of torts and professional negligenceACCA LW question bank · 12 chapters
More Breach of contract and remedies MCQs
- Q5Which of the following best describes the innocent party's duty to mitigate loss after a breach of contract?
- Q6In which situation is a court most likely to order specific performance?
- Q7An actress contracted exclusively with a film company and agreed not to act for any other company during the contract. She left to work…
- Q8An author was engaged to write a book for a series, and after he had done part of the work the publisher abandoned the series. What remedy…
- Q9Under the Limitation Act 1980, what is the normal limitation period for an action for breach of a simple contract?
