ACCA MA · Chapter 10 · Question 10 of 11
Which document sets out the instructions, procedures, timetable and responsibilities for preparing the budget?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) Budget manual
Explanation
The budget manual contains the rules and guidance for the budgeting process, including who is responsible for each budget and the timetable. The master budget is the final output (budgeted statement of profit or loss, statement of financial position and cash budget).
Practise all 11 Chapter 10 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 11 questions in Chapter 10Budgeting MCQs with answersNext chapter · Chapter 11Capital budgetingACCA MA question bank · 14 chapters
More Budgeting MCQs
- Q1What is the principal budget factor?
- Q2Budgeted sales for May are 12,000 units, and for June 10,000 units. Opening finished goods inventory on 1 May is 1,500 units. Closing…
- Q3Production for a period is budgeted at 12,500 units. Each unit uses 3 kg of material costing $2 per kg. Opening raw material inventory is…
- Q4Production is budgeted at 12,500 units. Each unit needs 0.6 standard direct labour hours. Idle time is expected to be 10% of hours paid…
- Q5Sales are made on credit and cash is received as follows: 20% in the month of sale (customers take a 2% discount), 50% in the following…