ACCA PM · Chapter 11 · Question 7 of 10
A company uses linear regression (y = a + bx) to estimate overhead costs (y, $000) from machine hours (x, 000 hours). From five observations: n = 5, sum of x = 50, sum of y = 500, sum of xy = 5,240 and sum of x squared = 540. Using b = (n sum xy - sum x sum y) / (n sum x^2 - (sum x)^2) and a = (sum y / n) - b(sum x / n), what is the forecast overhead cost when 15,000 machine hours are worked?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) $130,000
Explanation
b = (5 x 5,240 - 50 x 500) / (5 x 540 - 50^2) = (26,200 - 25,000) / (2,700 - 2,500) = 1,200 / 200 = 6. a = (500 / 5) - 6 x (50 / 5) = 100 - 60 = 40. Forecast y = 40 + (6 x 15) = 130, so overheads are $130,000.
Practise all 10 Chapter 11 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 10 questions in Chapter 11Quantitative analysis in budgeting MCQs with answersNext chapter · Chapter 12Standard costing and variance analysisACCA PM question bank · 14 chapters
More Quantitative analysis in budgeting MCQs
- Q9In the learning curve formula y = ax^b, b = log r / log 2. What is the value of b for a 90% learning curve (to three decimal places)?
- Q10Which of the following is a limitation of the high-low method of cost estimation?
- Q1The first unit of a new product took 100 hours to make. An 80% learning curve applies. What is the cumulative average time per unit when 8…
- Q2The first unit of a product took 50 hours. An 85% learning curve applies, and the learning index is b = log 0.85 / log 2 = -0.2345 (to…
- Q3The first batch of a new product took 200 hours. The first four batches took a total of 512 hours. What learning rate is being experienced?
