ACCA PM · Chapter 12 · Question 9 of 12
The standard labour time is 2 hours per unit at $12 per hour. Following new safety regulations that were not foreseen when the standard was set, a realistic standard would have been 2.5 hours per unit. Output was 1,800 units and 4,300 hours were worked. What is the labour efficiency operational variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) $2,400 favourable
Explanation
Revised standard hours for actual output = 1,800 x 2.5 = 4,500 hours. Operational efficiency variance = (4,500 - 4,300) x $12 = $2,400 favourable. The planning variance is (3,600 - 4,500) x $12 = $10,800 adverse, giving a total efficiency variance of $8,400 adverse.
Practise all 12 Chapter 12 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 12 questions in Chapter 12Standard costing and variance analysis MCQs with answersNext chapter · Chapter 13Performance measurement and controlACCA PM question bank · 14 chapters
More Standard costing and variance analysis MCQs
- Q11A purchasing manager buys a cheaper, lower-quality grade of material than standard. Which combination of variances is most likely to arise?
- Q12A company's standard selling price for product T is $50 per unit. During the period it sold 1,900 units at an average price of $48 per…
- Q1Which type of standard assumes perfect operating conditions, with no allowance for wastage, idle time or machine breakdowns?
- Q2A company bought and used 4,200 kg of material at a total cost of $23,100. The standard price is $5.20 per kg and the standard usage is 4…
- Q3Product W is made by mixing two materials. The standard input to produce 9 kg of W is 6 kg of D at $4 per kg and 4 kg of E at $7 per kg…
