CA Inter P4 · Chapter 12 · Question 8 of 10
Budgeted fixed overheads are ₹4,80,000 for a budgeted output of 24,000 units. Actual fixed overheads incurred were ₹4,95,000 and actual output was 22,500 units. The fixed overhead cost variance, and its split into expenditure and volume variances, is:
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) ₹45,000 (A), being expenditure ₹15,000 (A) and volume ₹30,000 (A)
Explanation
Standard rate = ₹4,80,000 / 24,000 = ₹20 per unit. Overheads absorbed = 22,500 x ₹20 = ₹4,50,000. Cost variance = absorbed - actual = ₹4,50,000 - ₹4,95,000 = -₹45,000, i.e. ₹45,000 Adverse. Expenditure variance = budgeted - actual = ₹4,80,000 - ₹4,95,000 = ₹15,000 Adverse. Volume variance = absorbed - budgeted = ₹4,50,000 - ₹4,80,000 = ₹30,000 Adverse. Check: 15,000 + 30,000 = 45,000.
Practise all 10 Chapter 12 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 10 questions in Chapter 12Standard Costing MCQs with answersNext chapter · Chapter 13Marginal CostingCA Inter P4 question bank · 14 chapters
More Standard Costing MCQs
- Q10An adverse material price variance is normally the responsibility of the:
- Q1Standard material for one unit of product is 4 kg at ₹25 per kg. Actual output was 2,000 units, using 8,300 kg purchased and consumed at…
- Q2Using the same data (standard 4 kg at ₹25 per unit; actual output 2,000 units; actual usage 8,300 kg at ₹24), the material usage variance…
- Q3With the same data, the material cost variance is:
- Q4Standard labour per unit is 3 hours at ₹60 per hour. Actual output was 1,800 units. Workers were paid for 5,700 hours at ₹62 per hour…
