CAF-5 · Chapter 16 · Question 6 of 10
If a company's average weekly demand for a component is 90 units, the expected lead time is 2 weeks, and management has decided to maintain a safety stock of 50 units, what is the appropriate Re-order Level?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) 230 units
Explanation
When a safety stock is maintained, the Re-order Level is calculated as: (Average Demand × Average Lead Time) + Safety Stock. Calculation: (90 units × 2 weeks) + 50 units = 180 + 50 = 230 units.
Practise all 10 Chapter 16 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 10 questions in Chapter 16Inventory Management MCQs with answersNext chapter · Chapter 17Mixed Practice Challenge ICAF-5 question bank · 18 chapters
More Inventory Management MCQs
- Q8If a company uses the Economic Order Quantity (EOQ) model and also maintains a permanent safety stock, how is the "average inventory…
- Q9Which of the following is an example of an "ordering cost" in inventory management?
- Q10Which of the following is a practical limitation or underlying assumption of the basic Economic Order Quantity (EOQ) model?
- Q1What is the primary objective of using the Economic Order Quantity (EOQ) model in inventory management?
- Q2Which of the following costs is typically classified as an inventory "holding cost" (or carrying cost)?