If a company's average weekly demand for a component is 90 units, the expected lead time is 2 weeks, and management has decided to maintain a safety stock of 50 units, what is the appropriate Re-order Level?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: B) 230 units

Explanation

When a safety stock is maintained, the Re-order Level is calculated as: (Average Demand × Average Lead Time) + Safety Stock. Calculation: (90 units × 2 weeks) + 50 units = 180 + 50 = 230 units.