CAF-5 · Chapter 17 · Question 1 of 20
(Standard Costing & Learning Curve) A company is introducing a new product and standard costs must be set. The first unit is expected to take 100 labour hours. The workforce is expected to follow an 80% learning curve. The standard labour rate is Rs. 50 per hour. During the first month, the company produces exactly 4 units, but the total actual labour hours worked were 270 hours. What is the Labour Efficiency Variance for the month?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) Rs. 700 Adverse
Explanation
Calculate the standard time for 4 units using the learning curve: Y=ax^b. b for 80% = log(0.8)/log(2)=-0.3219. Y=100*4^-0.3219 = 100*0.64 = 64 hours (Cumulative average time per unit). Total standard hours allowed for 4 units = 64*4 = 256 hours. Actual hours taken = 270 hours. Variance = (Standard Hours - Actual Hours) * Standard Rate = (256 - 270) * Rs. 50 = -Rs. 700 (Adverse, as actual time exceeded standard).
Practise all 20 Chapter 17 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 20 questions in Chapter 17Mixed Practice Challenge I MCQs with answersNext chapter · Chapter 18Mixed Practice Challenge IICAF-5 question bank · 18 chapters
More Mixed Practice Challenge I MCQs
- Q3(CVP Analysis & Limiting Factor) A company produces two products, X and Y. Product X yields a contribution of Rs. 40 per unit and requires…
- Q4(Marginal vs. Absorption Costing & Inventory Flow) A manufacturing firm has no opening inventory. During the year, it produced 10,000…
- Q5(Target Costing & Pricing) A company intends to launch a new product with a highly competitive target selling price of Rs. 500. The board…
- Q6(Process Costing & Abnormal Loss) In Process 1, 5,000 kg of materials were input at a total cost of Rs. 50,000. Conversion costs incurred…
- Q7(Inventory Management & Safety Stock) A company’s annual demand for a component is 120,000 units (assume 12 equal months). The cost of…
