(Labour Variances & High Day-Rate) Std labour rate Rs. 100/hr, 2 hrs per unit. New rate Rs. 120/hr. In first month, 5,000 units produced using 9,000 actual hours. What are the Labour Efficiency and Rate Variances?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: A) Efficiency: 100,000 Fav / Rate: 180,000 Adv

Explanation

Efficiency = (10,000 Std hrs - 9,000 Act hrs) * 100 = 100,000 Fav. Rate = (100 Std - 120 Act) * 9,000 = 180,000 Adv.