The CA Hub

CAF-5 · Chapter 3 · Question 8 of 10

When applying Activity-Based Costing, which cost driver should logically be used to assign "Machine set-up costs" to various products?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: D) Total number of batches or set-ups

Explanation

Machine set-up costs are incurred every time a machine is prepared for a new batch of production, regardless of how many units are in that batch. Therefore, the "Total number of batches" or "set-ups" is the correct driver.

Practise all 10 Chapter 3 questions