CIMA BA2 · Chapter 7 · Question 14 of 14
Variable production overheads are absorbed at $4 per labour hour worked, and the standard time is 2 labour hours per unit. In a period, employees were paid for 19,800 hours, but 600 of these hours were idle time because of a machine breakdown. Variable overheads are incurred only when labour is working. Actual output was 9,800 units. What is the variable overhead EFFICIENCY variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) $1,600 favourable
Explanation
Hours actually worked = 19,800 - 600 = 19,200. Standard hours for actual output = 9,800 x 2 = 19,600. Variable overhead efficiency variance = (19,600 - 19,200) x $4 = $1,600 favourable, because the output took fewer hours than standard. Using hours paid (19,800) would wrongly give $800 adverse; idle hours carry no variable overhead, so they are excluded.
Practise all 14 Chapter 7 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 14 questions in Chapter 7Standard costing and variance analysis MCQs with answersCIMA BA2 question bank · 12 chapters
More Standard costing and variance analysis MCQs
- Q2A company purchased 8,400 kg of material for $39,480. The standard price is $4.80 per kg. What is the material price variance?
- Q3A company produced 2,000 units in a period. The standard usage is 4 kg of material per unit at a standard price of $4.80 per kg, and 8,300…
- Q4A team was paid $63,900 for 3,600 hours worked. The standard rate is $17.50 per hour and each unit should take 3 standard hours. Output…
- Q5Employees were paid for 5,000 hours, but because of a machine breakdown only 4,700 hours were worked. The standard rate is $15 per hour…
- Q6Variable production overheads are absorbed at $6 per labour hour worked. In a period, 4,700 labour hours were worked and actual variable…
