A builder agrees to complete work for a fixed price. Midway, the client, worried about delay penalties under its own contract, promises extra payment if the builder finishes on time. The builder does so. Under English law, which case most supports the builder enforcing the extra payment?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: B) Williams v Roffey Bros, because the client obtained a practical benefit and there was no duress

Explanation

Performing an existing contractual duty owed to the promisor is generally not good consideration (Stilk v Myrick). However, Williams v Roffey Bros held that where the promisor obtains a practical benefit, such as avoiding a penalty clause, and there is no economic duress or fraud, the promise of extra payment can be enforced. Foakes v Beer concerns part payment of debts.

Practise all 10 Chapter 10 questions

Answer them one by one with instant feedback. Your score and mistakes are saved.

More Law of contract: formation MCQs

Sponsored slot availableRun a CA academy or hiring firm? Put your name in front of students preparing for this exam.Advertise →