CIMA BA4 · Chapter 11 · Question 8 of 10
Under English law, what is the effect of a valid liquidated damages clause?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) The innocent party recovers the agreed sum on breach, regardless of whether actual loss is higher or lower
Explanation
A liquidated damages clause fixes in advance the sum payable on breach. If valid, the agreed sum is recoverable whether actual loss turns out to be greater or smaller, and the innocent party need not prove its loss. Following Cavendish Square Holding v Makdessi (2015), a clause is an unenforceable penalty only if it imposes a detriment out of all proportion to any legitimate interest of the innocent party in performance; it no longer has to be a strict genuine pre-estimate of loss.
Practise all 10 Chapter 11 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
More Law of contract: terms, breach and remedies MCQs
- Q10Under English law, a ship is chartered for 24 months. Due to the owner's breach of a term requiring the ship to be 'seaworthy', the ship…
- Q1Under English law, what is the remedy for breach of a warranty?
- Q2Under English law, what is the standard limitation period for bringing an action for breach of a simple contract?
- Q3Under English law, which of the following is an equitable remedy?
- Q4A contract states that the seller will deliver goods by 1 June. On 1 May, the seller tells the buyer it will not deliver at all. Under…