US CMA Part 1 · Chapter 2 · Question 22 of 30

Which budgeting approach explicitly builds expected continuous improvements, such as planned cost reductions each period, into the budget figures?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: C) Kaizen budgeting

Explanation

Kaizen budgeting incorporates expected continuous improvement into budget estimates, for example assuming that the cost per unit will fall by a set percentage each quarter. The other approaches do not specifically embed improvement targets.