A business received an advance of Rs. 1.8 million against a total annual maintenance contract of Rs. 3.6 million. The contract runs for 9 months. After 4 months, what is the amount of unearned income (pre-received income)?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) Rs. 0.2 million
Explanation
Total contract is 3.6m for 9 months (0.4m per month). Revenue earned in 4 months = 0.4m x 4 = 1.6m. Advance received = 1.8m. Unearned income = Advance received (1.8m) - Revenue earned (1.6m) = Rs. 0.2 million.
Practise all 100 Chapter 10 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 100 questions in Chapter 10Preparation of Financial Statements MCQs with answersPRC-1 question bank · 10 chapters
More Preparation of Financial Statements MCQs
- Q14The proprietor of a business withdraws goods costing Rs. 4,000 for personal use. No entry was made. What adjusting entry is required?
- Q15A business has Trade Receivables of Rs. 100 million. A customer owing Rs. 1 million has gone bankrupt and must be written off. The…
- Q16In a partnership, Partner A and Partner B share profits equally. There is no interest on capital, but Partner B is entitled to a monthly…
- Q17When an entity prepares an 'Adjusted Trial Balance', what does this specific document represent?
- Q18Which of the following describes the correct accounting treatment for 'Carriage Inwards'?