When prioritising tasks, which type of task should generally be dealt with first?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: A) Tasks that are both urgent and important

Explanation

A common time management approach classifies tasks by urgency and importance. Urgent and important tasks need immediate attention. Important but non-urgent tasks should be scheduled, urgent but unimportant tasks may be delegated, and tasks that are neither should be minimised. Choosing tasks just because they are quick can mean important work is neglected.