ACCA BT · Chapter 13 · Question 8 of 10
Team members working on a cross-functional project are in conflict about deadlines. Their manager encourages them to openly explore the underlying concerns of both sides to find a solution that fully satisfies each party. Which conflict-handling approach is this?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) Collaborating
Explanation
Collaborating is assertive and cooperative: parties work together to find a solution that fully meets both sets of concerns, a 'win-win' outcome. Compromising involves each side giving up something, accommodating means one party gives way to the other, and avoiding means withdrawing from the conflict without resolving it.
Practise all 10 Chapter 13 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 10 questions in Chapter 13Personal effectiveness and communication MCQs with answersNext chapter · Chapter 14Professional ethics in accounting and businessACCA BT question bank · 14 chapters
More Personal effectiveness and communication MCQs
- Q10Which of the following best describes the purpose of a personal development plan (PDP)?
- Q1Which of the following is the best description of SMART objectives?
- Q2When prioritising tasks, which type of task should generally be dealt with first?
- Q3Which of the following is the main difference between coaching and mentoring?
- Q4In a basic model of communication, what is the term for anything that interferes with the message as it passes from sender to receiver?