CAF-5 · Chapter 11 · Question 9 of 10
During a period, workers were paid for 4,200 total hours, but the actual active production time was only 4,100 hours due to unexpected machine breakdowns. If the standard labour rate is Rs. 100 per hour, what is the idle time variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) Rs. 10,000 Adverse
Explanation
Idle time variance is calculated by taking the difference between hours paid and hours worked (the idle hours) and multiplying by the standard labour rate. Idle hours = 4,200 paid – 4,100 worked = 100 hours. 100 hours × Rs. 100 = Rs. 10,000. Idle time variance is always an Adverse variance.
Practise all 10 Chapter 11 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 10 questions in Chapter 11Variance Analysis MCQs with answersNext chapter · Chapter 12Target CostingCAF-5 question bank · 18 chapters
More Variance Analysis MCQs
- Q1What does the "total direct material cost variance" essentially represent in standard costing?
- Q2A company's standard material price is Rs. 8.00 per kg. During the month, it purchased and consumed 50,000 kgs of material at an actual…
- Q3Product X has a standard labour requirement of 4 hours per unit at a standard rate of Rs. 50 per hour. During the period, 1,000 units were…
- Q4Under an absorption costing system, how is the "fixed production overhead volume variance" calculated?
- Q5The fixed production overhead volume variance can be further sub-divided into which of the following two variances?
