CAF-5 · Chapter 11 · Question 5 of 10
The fixed production overhead volume variance can be further sub-divided into which of the following two variances?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) Capacity variance and Efficiency variance
Explanation
The study text explicitly states that the fixed production overhead volume variance can be further analyzed and sub-divided into two variances: capacity variance and efficiency variance.
Practise all 10 Chapter 11 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 10 questions in Chapter 11Variance Analysis MCQs with answersNext chapter · Chapter 12Target CostingCAF-5 question bank · 18 chapters
More Variance Analysis MCQs
- Q7When a manufacturing process requires a blend of two or more raw materials, the overall material usage variance can be further analyzed by…
- Q8A company uses a standard costing system. The standard material cost is Rs. 40 per kg. For a given period, the material usage variance was…
- Q9During a period, workers were paid for 4,200 total hours, but the actual active production time was only 4,100 hours due to unexpected…
- Q10A factory budgeted its fixed production overheads at Rs. 168,000 for the period. The actual fixed overheads incurred were Rs. 170,000…
- Q1What does the "total direct material cost variance" essentially represent in standard costing?