The CA Hub

CAF-5 · Chapter 11 · Question 5 of 10

The fixed production overhead volume variance can be further sub-divided into which of the following two variances?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: D) Capacity variance and Efficiency variance

Explanation

The study text explicitly states that the fixed production overhead volume variance can be further analyzed and sub-divided into two variances: capacity variance and efficiency variance.

Practise all 10 Chapter 11 questions

Answer them one by one with instant feedback. Your score and mistakes are saved.

More Variance Analysis MCQs