Saturn Limited imports raw materials with the following usage and lead time parameters: Maximum usage is 5,000 units per month, minimum usage is 3,000 units per month, maximum lead time is 4 months, and minimum lead time is 2 months. Using the standard formula, what should be the Re-order Level (ROL) for this raw material?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) 20,000 units
Explanation
The standard formula for establishing a Re-order Level to prevent stock-outs under maximum expected conditions is: Maximum Usage × Maximum Lead Time. Calculation: 5,000 units × 4 months = 20,000 units.
Practise all 10 Chapter 16 questions
Answer them one by one with instant feedback. Your score and mistakes are saved.
All 10 questions in Chapter 16Inventory Management MCQs with answersNext chapter · Chapter 17Mixed Practice Challenge ICAF-5 question bank · 18 chapters
More Inventory Management MCQs
- Q6If a company's average weekly demand for a component is 90 units, the expected lead time is 2 weeks, and management has decided to…
- Q7When evaluating whether to accept a bulk purchase discount from a supplier, which of the following financial trade-offs must be assessed?
- Q8If a company uses the Economic Order Quantity (EOQ) model and also maintains a permanent safety stock, how is the "average inventory…
- Q9Which of the following is an example of an "ordering cost" in inventory management?
- Q10Which of the following is a practical limitation or underlying assumption of the basic Economic Order Quantity (EOQ) model?