ACCA MA · Chapter 12 · Question 10 of 10
Each unit of a product uses 3 kg of material at $4 per kg and 2 direct labour hours at $12 per hour. Variable overheads are $3 per labour hour and fixed overheads are absorbed at $5 per labour hour. What is the standard full (absorption) production cost per unit?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) $52
Explanation
Materials 3 x 4 = $12; labour 2 x 12 = $24; variable overhead 2 x 3 = $6; fixed overhead 2 x 5 = $10. Standard full cost = 12 + 24 + 6 + 10 = $52. The standard marginal cost would be $42, excluding fixed overhead. Both overhead rates are per labour hour, so they must be multiplied by 2 hours.
More Standard costing and cost variances MCQs
- Q2A company bought 8,000 kg of material for $35,200, and 7,600 kg were used in production. The standard price is $4.50 per kg, and raw…
- Q3The standard material usage is 4 kg per unit, at a standard price of $4.50 per kg. 1,900 units were produced using 7,850 kg, which were…
- Q4Employees were paid $39,600 for 2,200 hours. Of these paid hours, 2,090 were worked and 110 were idle time. The standard labour rate is…
- Q5The standard labour time is 1.5 hours per unit, at $16 per hour. During a period 1,400 units were produced. Employees were paid for 2,300…
- Q6Variable production overhead is absorbed at a standard rate of $4 per direct labour hour. In a period, 3,150 labour hours were worked, the…
