The original budget for 10,000 units included: variable costs $60,000; semi-variable costs $35,000 (of which $15,000 is fixed); and fixed costs $40,000. Actual output was 12,000 units. What is the total flexed budget cost?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) $151,000
Explanation
Variable cost per unit = $60,000 / 10,000 = $6; flexed = 12,000 x $6 = $72,000. Semi-variable: variable element $20,000 / 10,000 = $2 per unit, so 12,000 x $2 = $24,000 plus $15,000 fixed = $39,000. Fixed costs stay at $40,000. Total = $72,000 + $39,000 + $40,000 = $151,000.
More Budgetary systems and types of budget MCQs
- Q9Hopwood identified three styles of using budget information to evaluate managers. Under which style is a manager judged mainly on the…
- Q1Which of the following is the main criticism of incremental budgeting?
- Q2Under zero-based budgeting, what is a decision package?
- Q3For which of the following types of cost is zero-based budgeting most likely to be useful?
- Q4A company prepares a 12-month budget. At the end of each month, it adds a budget for the same month of the following year and revises the…