CA Inter P4 · Chapter 11 · Question 4 of 8
Which of the following is the appropriate cost unit for an electricity supply undertaking?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) Kilowatt-hour
Explanation
Electricity is generated and supplied in kilowatt-hours (kWh), so the cost per kWh is the relevant measure. Room-day is used in hotels and cubic metre in earthmoving or construction-type services.