The factor that limits the activities of an organisation over the budget period and therefore determines the order in which functional budgets are prepared is known as the:
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) Principal budget factor
Explanation
The principal (key or limiting) budget factor, often sales demand but sometimes materials, labour or machine capacity, restricts the level of activity. The budget for that factor is prepared first and the other functional budgets are built around it.
More Budgets and Budgetary Control MCQs
- Q1The overheads of a factory are ₹3,36,000 at 60% capacity and ₹4,08,000 at 80% capacity. Assuming overheads are semi-variable and behave…
- Q2Budgeted sales for the quarter are 24,000 units. Opening stock of finished goods is 3,000 units and the desired closing stock is 4,500…
- Q3Budgeted production is 25,500 units and each unit needs 2 kg of raw material. Opening stock of raw material is 6,000 kg and the desired…
- Q4Sales are budgeted at ₹4,00,000 for August, ₹5,00,000 for September and ₹6,00,000 for October. 20% of sales are for cash; 50% of sales are…