Budgeted factory overheads are ₹6,30,000 and budgeted prime cost is ₹21,00,000. Overheads are absorbed as a percentage of prime cost. A job has a prime cost of ₹48,000. The overheads to be absorbed by the job are:

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: D) ₹14,400.00

Explanation

Absorption rate = ₹6,30,000 / ₹21,00,000 x 100 = 30% of prime cost. Overheads for the job = 30% x ₹48,000 = ₹14,400.