The CA Hub

CA Inter P4 · Chapter 6 · Question 2 of 9

Prime cost is ₹5,25,000 and factory overheads are ₹1,40,000. Opening work-in-progress is ₹30,000 and closing work-in-progress is ₹45,000. The works (factory) cost is:

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: A) ₹6,50,000

Explanation

Gross works cost = prime cost + factory overheads = ₹5,25,000 + ₹1,40,000 = ₹6,65,000. Works cost = gross works cost + opening WIP - closing WIP = ₹6,65,000 + ₹30,000 - ₹45,000 = ₹6,50,000.