The CA Hub

CA Inter P4 · Chapter 7 · Question 5 of 8

The entry to record factory overheads absorbed into production in the cost ledger is:

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: C) Dr Work-in-Progress Control A/c; Cr Factory Overhead Control A/c

Explanation

Overheads actually incurred are debited to Factory Overhead Control. When they are absorbed into production at the predetermined rate, Work-in-Progress Control is debited and Factory Overhead Control credited. Any balance left on the overhead control account represents under- or over-absorption.

All 8 questions in Chapter 7Cost Accounting Systems MCQs with answers

More Cost Accounting Systems MCQs

Sponsored slot availableRun a CA academy or hiring firm? Put your name in front of students preparing for this exam.Advertise →