CA Inter P6 · Chapter 7 · Question 9 of 10
When NPV and IRR rank two mutually exclusive projects differently, NPV is usually preferred because:
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) NPV assumes intermediate cash flows are reinvested at the cost of capital, which is more realistic than IRR's assumption of reinvestment at the IRR itself
Explanation
Both methods are discounted cash flow techniques. Rankings can conflict because of differences in project size or timing of cash flows. NPV implicitly assumes reinvestment at the cost of capital, while IRR assumes reinvestment at the project's own IRR, which may be unrealistically high. NPV also measures the absolute addition to shareholder wealth. Multiple IRRs arise only with non-conventional cash flows.
More Investment Decisions MCQs
- Q1A project costs ₹ 5,00,000 and is expected to generate cash inflows of ₹ 1,20,000, ₹ 1,50,000, ₹ 1,80,000, ₹ 2,00,000 and ₹ 1,60,000 in…
- Q2A machine costing ₹ 10,00,000 is expected to generate cash inflows after tax of ₹ 3,50,000 a year for 4 years, with no salvage value. The…
- Q3A project has a present value of cash inflows of ₹ 11,09,500 and an initial outlay of ₹ 10,00,000. Its profitability index is:
- Q4A project has an NPV of ₹ 18,000 at a 12% discount rate and an NPV of -₹ 6,000 at 16%. Using linear interpolation, its IRR is approximately:
- Q5Equipment costs ₹ 6,00,000, has a 5-year life and a salvage value of ₹ 1,00,000. The average annual profit after depreciation and tax is ₹…
