Under Section 74, if a sum is named as the amount to be paid in case of breach, the party complaining is entitled to:
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) Reasonable compensation not exceeding the amount so named.
Explanation
Unlike English law, Pakistani law allows the court to award 'reasonable compensation' up to the limit of the sum named, whether actual damage is proved or not.