CAF-5 · Chapter 11 · Question 3 of 10
Product X has a standard labour requirement of 4 hours per unit at a standard rate of Rs. 50 per hour. During the period, 1,000 units were produced using 4,050 actual hours. What is the direct labour efficiency variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) Rs. 2,500 Adverse
Explanation
Labour Efficiency Variance = (Standard Hours allowed for actual production – Actual Hours worked) × Standard Rate. Standard hours for 1,000 units = 1,000 × 4 = 4,000 hours. Calculation: (4,000 hours – 4,050 hours) × Rs. 50 = (50 hours) × 50 = Rs. 2,500. Because actual hours exceeded standard hours, the variance is Adverse.
More Variance Analysis MCQs
- Q5The fixed production overhead volume variance can be further sub-divided into which of the following two variances?
- Q6When preparing an operating statement to reconcile budgeted profit with actual profit under a standard marginal costing system, how must…
- Q7When a manufacturing process requires a blend of two or more raw materials, the overall material usage variance can be further analyzed by…
- Q8A company uses a standard costing system. The standard material cost is Rs. 40 per kg. For a given period, the material usage variance was…
- Q9During a period, workers were paid for 4,200 total hours, but the actual active production time was only 4,100 hours due to unexpected…
