CAF-5 · Chapter 18 · Question 13 of 20
(Labour Variances & High Day-Rate) Std labour rate Rs. 100/hr, 2 hrs per unit. New rate Rs. 120/hr. In first month, 5,000 units produced using 9,000 actual hours. What are the Labour Efficiency and Rate Variances?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) Efficiency: 100,000 Fav / Rate: 180,000 Adv
Explanation
Efficiency = (10,000 Std hrs - 9,000 Act hrs) * 100 = 100,000 Fav. Rate = (100 Std - 120 Act) * 9,000 = 180,000 Adv.
More Mixed Practice Challenge II MCQs
- Q15(Relevant Costing & Further Processing under Capacity Constraints) Joint Product Alpha sells for Rs. 50 at split-off or Rs. 80 as…
- Q16(Inventory Management: Safety Stock & Lead Time Probabilities) Consumption is 100 units/day. Lead time is normally 5 days (60%), 6 days…
- Q17(Simultaneous Equations & Factory Overheads) Dept P costs = Rs. 100,000 + 10% Q. Dept Q costs = Rs. 80,000 + 20% P. What is the total cost…
- Q18(Standard Costing: Working Backwards for Material Price) Price Variance is Rs. 12,000 Adverse. Usage Variance is Rs. 8,000 Favourable. Std…
- Q19(CVP Analysis: Margin of Safety Ratio) C/S ratio 40%. Fixed costs Rs. 600,000. Operating at Margin of Safety of 25%. What is the actual…
