CAF-5 · Chapter 2 · Question 8 of 10

A production department has budgeted factory overheads of Rs. 360,000 and expects to work 8,000 direct labour hours. What is the overhead absorption rate (OAR) per direct labour hour?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: A) Rs. 45.00

Explanation

The Overhead Absorption Rate (OAR) is calculated as Budgeted Factory Overheads divided by Budgeted Base (Direct Labour Hours). Calculation: Rs. 360,000 / 8,000 hours = Rs. 45.00 per hour.