The CA Hub

CAF-5 · Chapter 6 · Question 4 of 10

In a job costing system, what is the correct double entry to record the issuance of direct materials from the store to a specific job (e.g., Job 123)?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: D) Debit: Work in Process - Job 123 / Credit: Materials Control

Explanation

When direct materials are issued to a specific job, their cost becomes part of the active production for that job. Therefore, the WIP account for the specific job is debited, and the Materials Control account is credited.