CAF-7 · Chapter 13 · Question 8 of 15
A business faces a choice between two mutually exclusive projects. Project X has an NPV of Rs. 50,000 and an IRR of 18%. Project Y has an NPV of Rs. 70,000 and an IRR of 14%. The company's cost of capital is 10%. Which project should the company accept?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) Project Y, because its absolute NPV is higher
Explanation
When NPV and IRR give conflicting rankings for mutually exclusive projects, the NPV rule must always prevail. NPV measures the absolute increase in shareholder wealth (Rs. 70,000), which is the primary objective of financial management.
More Introduction to Project Appraisal MCQs
- Q10When dealing with inflation in an NPV calculation, what is the fundamental rule for matching cash flows to discount rates?
- Q11A company is forced to reject a highly profitable project because its internal Board of Directors has imposed a strict limit on the…
- Q12What does a 'Perpetuity Factor' allow a financial analyst to calculate?
- Q13A business is evaluating a project. General fixed overheads of the head office, amounting to Rs. 200,000, have been allocated to this…
- Q14At the end of a project's life, a machine is sold for Rs. 50,000. Its remaining Tax Written Down Value (WDV) is Rs. 80,000. Under the tax…
