In which of the following situations would overheads DEFINITELY be under-absorbed, assuming a predetermined absorption rate based on budgeted activity?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) Actual overheads are higher than budgeted and actual activity is lower than budgeted
Explanation
Absorbed overhead = predetermined rate x actual activity. If activity is below budget, less than the budgeted overhead is absorbed; if actual spending is also above budget, actual overhead must exceed the absorbed amount, so under-absorption is certain. In the other situations the result is over-absorption or depends on the size of the two differences.
More Accounting for overheads MCQs
- Q2Factory rent of $84,000 is apportioned on the basis of floor area. The floor areas of the cost centres are: Machining 2,400 m2, Assembly…
- Q3The overheads of the Maintenance service cost centre total $36,000. Maintenance work is used as follows: Production department P1 60%…
- Q4A factory has two production departments (P1 and P2) and two service departments (X and Y). Overheads allocated and apportioned so far are…
- Q5A production department is highly automated, and most of its overhead costs relate to running its machines. Which basis is most…
- Q6Budgeted production overheads were $450,000 and budgeted direct labour hours were 60,000. Overheads are absorbed on a labour hour basis…