CIMA BA2 · Chapter 5 · Question 4 of 10
A process was charged with 10,000 kg of material costing $46,000 and conversion costs of $18,000. Normal loss is 8% of input and can be sold as scrap for $2 per kg. Actual output was 9,100 kg. What is the cost per kg of expected output, to the nearest cent?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) $6.78
Explanation
Expected output = 10,000 x 92% = 9,200 kg. Normal loss = 800 kg with scrap value 800 x $2 = $1,600. Cost per kg = ($46,000 + $18,000 - $1,600) / 9,200 = $62,400 / 9,200 = $6.7826, which is $6.78 to the nearest cent. Actual output is not used in calculating the rate; the 100 kg shortfall is an abnormal loss valued at this rate.
More Job, batch and process costing MCQs
- Q6Input to a process was 5,000 litres at a total cost of $27,000. Normal loss is 10% of input and is sold as scrap for $1.50 per litre…
- Q7A process has no opening work in progress. During the period 9,000 units were started, of which 7,400 were completed. The 1,600 units in…
- Q8A process has no opening work in progress. During the period 9,000 units were started, of which 7,400 were completed. The 1,600 units in…
- Q9Which of the following features distinguishes PROCESS costing from job costing?
- Q10In a process account, how are normal losses and abnormal losses valued?