CIMA BA2 · Chapter 7 · Question 6 of 14
Variable production overheads are absorbed at $6 per labour hour worked. In a period, 4,700 labour hours were worked and actual variable overheads were $29,000. What is the variable overhead EXPENDITURE variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) $800 adverse
Explanation
Expected variable overhead for the hours actually worked = 4,700 x $6 = $28,200. Actual expenditure = $29,000. Expenditure variance = $29,000 - $28,200 = $800 adverse, because more was spent than standard for the hours worked.
More Standard costing and variance analysis MCQs
- Q8A company uses standard MARGINAL costing. Budgeted fixed production overheads were $120,000, based on budgeted production of 10,000 units…
- Q9A company sold 5,200 units for total revenue of $247,000. The standard selling price is $50 per unit. What is the sales price variance?
- Q10Budgeted sales were 6,000 units but actual sales were 5,200 units. The standard selling price is $50, the standard variable cost is $28…
- Q11A company reports a favourable material price variance and an adverse material usage variance in the same period. Which of the following…
- Q12The labour efficiency variance for a period was $2,400 favourable. The standard rate is $16 per hour, the standard time is 1.5 hours per…
