A company's maintenance cost has been estimated by regression as: Cost = $12,500 + $3.40 x machine hours. What is the forecast maintenance cost for a month in which 8,000 machine hours are expected?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: A) $39,700

Explanation

Forecast cost = fixed component + variable rate x activity = $12,500 + $3.40 x 8,000 = $12,500 + $27,200 = $39,700.