A construction company has won a three-year contract to build a hospital. Which type of budget is most appropriate for planning and controlling the costs of this contract?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: D) A project budget covering the entire life of the contract

Explanation

A project budget is prepared for a specific, one-off undertaking and spans the full life of the project, which may cross several fiscal years. The annual master budget covers the whole company for a single year and does not isolate the project.