US CMA Part 1 · Chapter 3 · Question 4 of 30
Budgeted sales were 6,000 units of Product X (contribution margin $20 per unit) and 4,000 units of Product Y (contribution margin $35 per unit). Actual sales were 7,700 units of X and 3,300 units of Y. What is the sales mix variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) $16,500 unfavorable
Explanation
Budgeted mix is 60% X / 40% Y; actual total units = 11,000, with an actual mix of 70% X / 30% Y. Mix variance = sum of (actual mix % - budgeted mix %) x actual total units x budgeted CM per unit. X: (70% - 60%) x 11,000 x $20 = $22,000 F. Y: (30% - 40%) x 11,000 x $35 = $38,500 U. Net = $16,500 unfavorable, because the mix shifted toward the lower-margin product. (The sales quantity variance would be 1,000 x $26 = $26,000 favorable.)
More Performance Management MCQs
- Q6To produce 23,500 units, a factory used 48,500 pounds of material. The standard is 2 pounds per unit at $3.00 per pound. What is the…
- Q7Direct labor for the month was 12,400 hours at a total cost of $327,360. The standard wage rate is $26 per hour, and standard hours…
- Q8A plant produced 25,000 units, each with a standard of 0.5 direct labor hours at $26 per hour. Actual hours worked were 12,400, at an…
- Q9A chemical is made by blending two inputs. The standard mix for a 100 kg input batch is 60 kg of Input A at $2.00 per kg and 40 kg of…
- Q10Variable overhead is applied at $4.80 per direct labor hour. Actual variable overhead was $61,200, actual hours were 12,400 and standard…
