US CMA Part 1 · Chapter 4 · Question 19 of 22
A plant applies the theory of constraints. A single machine is the bottleneck. Data per unit: Alpha: price $120, direct materials $50, bottleneck time 5 minutes Beta: price $90, direct materials $30, bottleneck time 3 minutes Gamma: price $150, direct materials $60, bottleneck time 8 minutes All other costs are fixed in the short run. To maximize throughput, which product should receive priority on the bottleneck?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) Beta, with throughput contribution of $20.00 per bottleneck minute
Explanation
Under the theory of constraints, throughput contribution = selling price - direct materials, and products are ranked by throughput per unit of the constrained resource. Alpha: ($120 - $50) / 5 = $14.00 per minute; Beta: ($90 - $30) / 3 = $20.00 per minute; Gamma: ($150 - $60) / 8 = $11.25 per minute. Beta earns the most per bottleneck minute, so it should be prioritized.
More Cost Management MCQs
- Q21In a Six Sigma improvement project, what do the letters of the DMAIC methodology stand for?
- Q22Which statement best describes life-cycle costing?
- Q1In its first year, a company produced 50,000 units and sold 46,000 units. Fixed manufacturing overhead was $600,000; there were no…
- Q2Per-unit costs for a product are: direct materials $14, direct labor $9, variable manufacturing overhead $5, fixed manufacturing overhead…
- Q3Which cost is treated as a product cost under absorption costing but as a period cost under variable costing?