In a risk heat map that plots likelihood against impact, which risks should generally receive the highest priority for management attention?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: D) Risks with both high likelihood and high impact

Explanation

A heat map shows each risk's assessed likelihood and impact. Those in the high-likelihood, high-impact zone pose the greatest threat to objectives and are prioritized for response. Low-impact frequent risks may be handled through routine controls, while low-likelihood, high-impact risks often call for contingency plans or insurance.