US CMA Part 2 · Chapter 8 · Question 9 of 15
Two mutually exclusive projects of the same size and life are being evaluated. Project M has the higher NPV at the firm's cost of capital, while Project N has the higher IRR. Which project should be selected, and why?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) Project M, because NPV measures the increase in shareholder wealth and assumes reinvestment at the cost of capital
Explanation
When NPV and IRR rank mutually exclusive projects differently (because of differences in timing of cash flows or scale), the NPV ranking should be followed. NPV measures the absolute increase in wealth and implicitly assumes reinvestment at the cost of capital, whereas IRR assumes reinvestment at the IRR itself, which is often unrealistic.
More Capital investment decisions MCQs
- Q11Upton Robotics invests $300,000 in a project producing after-tax cash inflows of $120,000 at the end of each of the next 4 years. The…
- Q12A financial analyst recalculates a project's NPV several times, changing only the sales volume assumption each time while holding all…
- Q13Which statement best describes Monte Carlo simulation in capital budgeting?
- Q14A mining company's project has a slightly negative NPV based on expected cash flows, but the company can abandon the project and sell the…
- Q15Vernon Corp. has a capital budget of $1,000,000. Its independent projects cannot be divided: Project A: cost $600,000, NPV $150,000…
