ICAEW BIP · Chapter 6 · Question 8 of 11

What is a fixed budget?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: C) A budget prepared for a single, planned level of activity, which is not adjusted when actual activity differs

Explanation

A fixed budget is set for one planned level of activity. It is useful for planning but can be misleading for control, because comparing actual results at a different activity level with it mixes up volume effects and efficiency effects. A budget designed to change with activity is a flexible budget.