ICAEW BIP · Chapter 9 · Question 6 of 13
Variable production overheads are absorbed at a standard rate of £5 per labour hour worked. In the period, 4,900 labour hours were worked and actual variable overheads were £26,100. What is the variable overhead expenditure variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) £1,600 adverse
Explanation
Expected variable overhead for the hours worked = 4,900 x £5 = £24,500. Actual = £26,100. Expenditure variance = £24,500 - £26,100 = £1,600 adverse. Hours worked are used because variable overheads are assumed not to be incurred during idle time.
More Standard costing and variance analysis MCQs
- Q8A company sold 4,600 units for total revenue of £262,200. The standard selling price is £55 per unit. What is the sales price variance?
- Q9Budgeted sales were 5,000 units and actual sales were 4,600 units. The standard contribution is £22 per unit and the standard profit is…
- Q10A company reports a favourable material price variance and an adverse material usage variance. Which of the following is the most likely…
- Q11A company's budgeted profit for a period was £84,000. The operating statement shows total favourable variances of £15,300 and total…
- Q12A company bought 7,000 kg of material for £31,500. The material price variance was £2,100 adverse. What is the standard price per kg?
