Q3: Standard costing and variances

10 marksNumericalPass rate 46%

Working backwards from given variances to standard and actual material prices, standard hours, standard variable overhead per unit and the sales volume profit variance.

Read the question first

We don't reproduce ICAP's question. Open it in the official PDF, attempt it, then use this walkthrough.

Q3 in the official paper (p. 3) Official suggested answer Suggested answers and marking plans sit in ICAP's student area (CRN login required).Examiners' comments on Q3

How to approach it

  1. Write each variance formula and mark which pieces are known.
  2. Solve the usage variance first to get the standard price; then the price variance gives the actual price.
  3. Labour rate variance ÷ rate difference gives actual hours; the efficiency information then gives standard hours.
  4. Standard variable overhead per unit = rate per hour × standard hours per unit.
  5. Sales volume profit variance = change in units × standard profit per unit (not contribution, under absorption costing).

Key rules to apply

  • Usage variance = (SQ − AQ) × SP. Price variance = (SP − AP) × AQ.
  • Under absorption costing, sales volume variance uses standard profit; under marginal costing, standard contribution.

Common mistakes

Drawn from the examiners' comments for this sitting (summarised in our words) and from typical errors on this topic.

  • Adding a favourable price variance to the standard price instead of deducting it (examiners' point).
  • Using the overhead rate per hour as the cost per unit.
  • Using actual figures in the sales volume variance.

Similar question with worked solution

Written by us with our own numbers; it tests the same skills as Q3 without copying it.

Original practice question

Variances in reverse

A product's material price variance was Rs 60,000 F and usage variance Rs 60,000 A. 30,000 kg were used, 2,000 kg more than standard for the 4,000 units made. Labour: rate variance Rs 36,000 A, actual rate Rs 212 vs standard Rs 200; standard 0.8 hours per unit. Variable overhead is Rs 40 per standard hour. Fixed overhead is Rs 25 per unit. Standard selling price Rs 600. Budgeted sales were 3,600 units; actual sales 4,000.

Required: Find the standard and actual material prices, actual labour hours and the sales volume profit variance.

Worked solution

WorkingResult
Standard price: 60,000 ÷ 2,000 kgRs 30/kg
Actual price: 30 − 60,000 ÷ 30,000Rs 28/kg
Actual hours: 36,000 ÷ (212 − 200)3,000 hours
Standard material per unit: 28,000 ÷ 4,000 = 7 kg × 30Rs 210
Standard profit: 600 − 210 − 160 − 32 − 25Rs 173
Sales volume profit variance: 400 × 173Rs 69,200 F

Answer: Standard Rs 30/kg, actual Rs 28/kg, 3,000 hours, sales volume profit variance Rs 69,200 F.