Hunza Limited acquired an office building on 1 October 2014. Initial costs were: Land Rs. 2,000k, Building structure Rs. 10,000k (25 yr life), Air conditioning Rs. 4,000k (10 yr life, 500k RV). What is the total carrying amount at 31 March 2015?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: A) Rs. 15,625,000

Explanation

Time = 6 months. Land is not depreciated (2,000). Building depr = 10,000 / 25 * 6/12 = 200 (WDV = 9,800). AC depr = (4,000 - 500) / 10 * 6/12 = 175 (WDV = 3,825). Total = 2,000 + 9,800 + 3,825 = Rs. 15,625k.