PRC-3 · Chapter 10 · Question 58 of 70
The financial shortfall between the total energy generated by power plants and the actual energy successfully billed to consumers is known as:
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) Distribution & transmission losses
Explanation
T&D losses account for energy lost due to electrical resistance in wires (technical loss) and energy stolen via theft (non-technical loss).
More Demand, Supply and Market Equilibrium MCQs
- Q60When turbines generate electricity at the power plant, the voltage is immediately increased for efficient long-distance travel by passing…
- Q61In the Textile industry, the mechanical process dedicated to converting raw cotton or polyester fibers into continuous yarn is called:
- Q62The primary raw materials forming the backbone of the Pakistani Textile industry are naturally grown cotton, viscose, and:
- Q63The entire Pharmaceutical industry in Pakistan is officially regulated and monitored by which authority?
- Q64Extensive medical experiments undertaken to develop research evidence regarding the safety and efficacy of new medicines in treating human…