Before the date for performance, one party clearly states that it will not perform its obligations. What is this called and what may the innocent party do, as established in Hochster v De La Tour?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) Anticipatory breach; the innocent party may sue immediately without waiting for the performance date
Explanation
An anticipatory breach occurs when a party indicates, before performance is due, that they will not perform. In Hochster v De La Tour the innocent party was allowed to sue for damages at once. Alternatively the innocent party may affirm the contract and wait for the date of performance, but then risks the contract being frustrated in the meantime (Avery v Bowden).
More Breach of contract and remedies MCQs
- Q3A laundry company bought a boiler that was delivered five months late. The seller knew the laundry needed it urgently but did not know of…
- Q4A contract states that if the builder finishes late it will pay 2,000 per week of delay. The amount was set after considering the client's…
- Q5Which of the following best describes the innocent party's duty to mitigate loss after a breach of contract?
- Q6In which situation is a court most likely to order specific performance?
- Q7An actress contracted exclusively with a film company and agreed not to act for any other company during the contract. She left to work…